[NEWS] Texas Utility Can Take Lufkin Biomass Power Facility Off-Line

– April 8, 2016, Platts

AspenPowerPlant_14032141490273

Photo: Biomass Magazine

Aspen Power can proceed to mothball a 50-MW biomass generation unit north of Houston without impairing reliability, the Electric Reliability Council of Texas said Friday.

Aspen Power announced plans on March 17 to suspend operations at the Lufkin Generating Station because of “poor” economics in the market on July 6. Commissioned in August 2011, the plant is Texas’ first wood-based biomass power plant.

“ERCOT has completed its review and is issuing its initial determination that this Resource is not required to support ERCOT transmission system reliability (i.e. voltage support, stability or management of localized transmission constraints under first contingency criteria),” ERCOT said in an email to market participants.

Among other suspensions of operations announced for coming weeks include NRG Energy’s 371-MW Greens Bayou 5 natural gas-fired steam boiler generator, as of June 27, and a 75-MW gas peaker at its 3,687-MW WA Parish power plant in southwest Houston on May 19.

One comment

  • Texas Prairie Dog

    if I recall correctly the city of Austin bought into this plant with little public input, and it’s never produced. thrown away money, at least there were no forests destroyed to run some idiot’s swimming pool pump.

    Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s