[NEWS] Why Biomass Remains a Challenge, Even in Timber-Rich Georgia

– by Gillian Neimark, June 16, 2017, Southeast Energy News

Albany Green biomass SE Energy NewsA new biomass plant under construction in Georgia highlights the challenging economics of the technology, even in a state so rich in forestry waste it exports it to other countries.

The 50 MW Albany Green plant – the largest renewable energy project in the state so far – is a unique collaboration among Georgia Power, private companies (including Procter & Gamble) and a nearby Marine base. While the cost for biomass generated electricity is too high to compete with wind and solar, the project also produces steam for industrial use, which improves its economics.

Because Albany Green is situated in the midst of rich timber tracts, biomass harvesting will be restricted to a 100 mile radius, and will include forestry residues locally sourced that would otherwise have been left to decay, burn or dispose of in a landfill. This includes trees not suitable for saw or pulp mills, discarded tree tops, limbs or branches, sawdust, mill waste, demolition debris and the seasonally available shells of pecans and peanuts.

READ MORE at Southeast Energy News

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s