[NEWS] Hawaii Biomass Project Slated for December 2018

– by Tom Callis, August 9, 2017, Hawaii Tribune-Herald

Hu Honua Biomass Hawaii Tribune Herald

Photo: Hawaii Tribune-Herald

A Hu Honua Bioenergy official says construction of its biomass power plant near Pepeekeo is moving “full speed ahead” and is on track to be complete in December 2018.

The project recently was brought from the brink after the state Public Utilities Commission approved an amended power purchase agreement with Hawaii Electric Light Co. on July 28.

The utility previously canceled its contract with Hu Honua, which initially planned to be complete in January 2016, due to missed deadlines. The amended PPA is the result of a settlement agreement between the parties.

Harold Robinson, president of Island Energy, Hu Honua’s parent company, said construction resumed July 3 ahead of the ruling and the company is ramping up those efforts.

READ MORE at Hawaii Tribune-Herald 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s